Turap Kali Item Sisi Utara Jalan Sunter Kemayoran Ditinggikan

Sheet Pile on North Side of Jalan Sunter Kemayoran Elevated

We aims to finish it on February 28 by sending 10 personnel

The Tanjung Priok Sub-district Water Resources (SDA) Executing Unit, North Jakarta conducts the elevation of the Item River's sheet pile on the north side of Jalan Sunter Kemayoran, which is approximately 350 meters long.

Deny Tri Hendarto, Executing Unit Head of Tanjung Priok Sub-district SDA said the work had been carried out since January 5.

Collapsed Sheet Pile and Reservoir in Kramat Jati Being Repaired

"We aims to finish it on February 28 by sending 10 personnel," he expressed, Thursday (1/28).

He explained it was done to anticipate overflowing waters of Item River to RW 02 area, Sunter Jaya Urban Village.

"We have to do it, as the contour of the north side sheet pile is lower than the south side," he explained.

He added the sheet pile height was increased to 80 centimeters. Currently the work had been completed for 100 meters length.

"By doing so we expect the location can be free from the flooding when rain pours," he hoped.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye842 personTiyo Surya Sakti
  2. Posyandu-Posbindu Services Reach 1,600 Seniors and Toddlers in Utan Panjang

    access_time07-04-2026 remove_red_eye794 personFolmer
  3. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye787 personNurito
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye681 personTiyo Surya Sakti
  5. West Jakarta BPN Holds Mobile Land Service in Kembangan

    access_time06-04-2026 remove_red_eye636 personBudhi Firmansyah Surapati