Turap Kali Item Sisi Utara Jalan Sunter Kemayoran Ditinggikan

Sheet Pile on North Side of Jalan Sunter Kemayoran Elevated

We aims to finish it on February 28 by sending 10 personnel

The Tanjung Priok Sub-district Water Resources (SDA) Executing Unit, North Jakarta conducts the elevation of the Item River's sheet pile on the north side of Jalan Sunter Kemayoran, which is approximately 350 meters long.

Deny Tri Hendarto, Executing Unit Head of Tanjung Priok Sub-district SDA said the work had been carried out since January 5.

Collapsed Sheet Pile and Reservoir in Kramat Jati Being Repaired

"We aims to finish it on February 28 by sending 10 personnel," he expressed, Thursday (1/28).

He explained it was done to anticipate overflowing waters of Item River to RW 02 area, Sunter Jaya Urban Village.

"We have to do it, as the contour of the north side sheet pile is lower than the south side," he explained.

He added the sheet pile height was increased to 80 centimeters. Currently the work had been completed for 100 meters length.

"By doing so we expect the location can be free from the flooding when rain pours," he hoped.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2375 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1002 personAldi Geri Lumban Tobing
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye986 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye851 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye745 personBudhi Firmansyah Surapati