Turap Kali Item Sisi Utara Jalan Sunter Kemayoran Ditinggikan
....
photo Rezki Apriliya Iskandar - Beritajakarta.id

Sheet Pile on North Side of Jalan Sunter Kemayoran Elevated

We aims to finish it on February 28 by sending 10 personnel

The Tanjung Priok Sub-district Water Resources (SDA) Executing Unit, North Jakarta conducts the elevation of the Item River's sheet pile on the north side of Jalan Sunter Kemayoran, which is approximately 350 meters long.

Deny Tri Hendarto, Executing Unit Head of Tanjung Priok Sub-district SDA said the work had been carried out since January 5.

Collapsed Sheet Pile and Reservoir in Kramat Jati Being Repaired

"We aims to finish it on February 28 by sending 10 personnel," he expressed, Thursday (1/28).

He explained it was done to anticipate overflowing waters of Item River to RW 02 area, Sunter Jaya Urban Village.

"We have to do it, as the contour of the north side sheet pile is lower than the south side," he explained.

He added the sheet pile height was increased to 80 centimeters. Currently the work had been completed for 100 meters length.

"By doing so we expect the location can be free from the flooding when rain pours," he hoped.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye716 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye603 personFolmer
  3. 49,101 Local and Foreign Tourists Swarm Monas

    access_time02-04-2025 remove_red_eye290 personBudhi Firmansyah Surapati
  4. Transjakarta Ready to Support People's Mobility This Eid

    access_time30-03-2025 remove_red_eye253 personAldi Geri Lumban Tobing
  5. S. Jakarta Transportation Sub-agency Optimizes Services at Tourist Spots

    access_time03-04-2025 remove_red_eye251 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik