Channel in Kampung Melayu Kecil Dredged
access_time March 04 2021 10:44 PM remove_red_eye 1230
Reported by TP Moan Simanjuntak | Translated by Nugroho Adibrata
Reported by TP Moan Simanjuntak | Translated by Nugroho Adibrata
As a result, the channel cannot accommodate rainwater maximally
The Tebet Sub-district Water Resources (SDA) Task Force, South Jakarta began to dredge the 240-meter length water channel at Jalan Kampung Melayu Kecil II, RW 10, Bukit Duri Urban Village.
Tebet Sub-district SDA Sub-agency Executing Unit Head, Fachri expressed the mud thickness was already over 70 centimeters.
South Jakarta SDA Dredged Mud from Krukut River in Kemang III Park Area"As a result, the channel cannot accommodate rainwater maximally," he said, Thursday (3/4).
He explained as many as 12 personnel had been alerted to the location. They divided into three segments and each segment was worked on by six personnel.
"It has been ongoing since February 8. It is done as deep as one meter and will be complete in three months ahead," he stated.