Sidewalk Arrangement on Jalan Raya Ragunan Targeted to Be Completed in April
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
Sidewalk arrangement on Jalan Raya Ragunan, in front of Block D of PD. Pasar Jaya, Pasar Minggu, South Jakarta which has been carried out since March 27, is targeted to be completed by the end of April. This arrangement is carried out through collaboration between Bina Marga Sub-agency, Water Resources (SDA) Sub-agency, and City Park and Forestry Sub-agency.
Current progress has reached 50 percent
Pasar Minggu Sub-district Bina Marga Unit Coordinator, Rahman Hakim mentioned, arrangement implemented on sidewalk with length 56 meters and width 2.5 meters.
Bina Marga Personnel Repair Sidewalk on Jalan Setiabudi Raya"Current progress has reached 50 percent. We are targeting to finish it by the end of April," he said, Tuesday (4/13).
For this sidewalk arrangement work, his side deployed 8 personnel to install paving blocks and create six ditches.
Meanwhile, SDA personnel assisted in dredging mud sedimentation and building manhole. Then, City Park and Forestry Unit personnel built 50-centimeter parks on the left and right sides of the sidewalk.
"This arrangement is not only to beautify the area, but also to make pedestrian safer and more comfortable," he stated.