Perbaikan Turap Longsor di TPU Cijantung Capai 40 Persen

Collapsed Retaining Wall Repair in Cijantung Public Cemetery Reaches 40 Percent

Repair on retaining wall with length 10 meters and height 5 meters which collapsed in Cijantung Public Cemetery (TPU), Cijantung Urban Village, Pasar Rebo, East Jakarta has now touched 40 percent. This repair is targeted to be completed in the end of April.

We are targeting the repair work to finish in April

East Jakarta City Park and Forestry Sub-agency's Forestry and Green Belt Section Head, Atang Setiawan mentioned, the retaining wall was collapsed due to being eroded by continuous heavy rain in March. Repair was started in April because his side had to provide material first.

"Current progress has touched 40 percent. We are targeting the repair work to finish in April," he said, Wednesday (4/21).

Collapsed Retaining Wall Repair at Susukan Public Cemetery is Completed

His side deployed 8 East Jakarta City Park and Forestry Sub-agency Unit personnel to repair it by installing river stones and concrete tie beam (sloof) every three meters to strengthen the foundation.

"So far there are no obstacles in repairing it," he conveyed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1591 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1441 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1307 personFolmer
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye968 personDessy Suciati
  5. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye845 personAldi Geri Lumban Tobing