Collapsed Retaining Wall Repair in Cijantung Public Cemetery Reaches 40 Percent

Repair on retaining wall with length 10 meters and height 5 meters which collapsed in Cijantung Public Cemetery (TPU), Cijantung Urban Village, Pasar Rebo, East Jakarta has now touched 40 percent. This repair is targeted to be completed in the end of April.

We are targeting the repair work to finish in April

East Jakarta City Park and Forestry Sub-agency's Forestry and Green Belt Section Head, Atang Setiawan mentioned, the retaining wall was collapsed due to being eroded by continuous heavy rain in March. Repair was started in April because his side had to provide material first.

"Current progress has touched 40 percent. We are targeting the repair work to finish in April," he said, Wednesday (4/21).

Collapsed Retaining Wall Repair at Susukan Public Cemetery is Completed

His side deployed 8 East Jakarta City Park and Forestry Sub-agency Unit personnel to repair it by installing river stones and concrete tie beam (sloof) every three meters to strengthen the foundation.

"So far there are no obstacles in repairing it," he conveyed.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye782 personFakhrizal Fakhri
  2. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye713 personDessy Suciati
  3. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye622 personTiyo Surya Sakti
  4. Job Absorption Rises in Jakarta

    access_time17-04-2026 remove_red_eye615 personDessy Suciati
  5. Training and Certification Boost Tourism Workforce Competitiveness

    access_time17-04-2026 remove_red_eye596 personAldi Geri Lumban Tobing