 3000 Meter Kubik Lumpur Berhasil Diangkut dari Kali Grogol, Palmerah

3,000 Cubic Meters of Mud Transported from Kali Grogol River

The West Jakarta Water Resources (SDA) Sub-agency has started dredging the Kali Grogol River, Palmerah. So far, they have collected around 3,000 cubic meters of mud.

Previously the mud had a thickness of about 6,000-7,000 cubic meter

Drainage Maintenance Division Head, Wawan Kurniawan said, it has been conducted since May 12 and was targeted to be complete in the upcoming August.

"Previously the mud had a thickness of about 6,000-7,000 cubic meter," he expressed, Wednesday (7/21).

PPSU Cleans Up Channel on Jalan Malaka Munjul

He said it was dredged up to one kilometer with six meters width using an amphibious excavator.

It was carried out in the morning until the afternoon. Afterwards, the mud collected on the riverbank and then transported at night using a dump truck and dumped into Ancol area, North Jakarta.

"We also coordinate with the local regional apparatus where the work is done at night without any problems, especially to transport the mud," he stated.

Linked News
Popular News indeks
  1. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1146 personDessy Suciati
  2. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye928 personNurito
  3. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye834 personDessy Suciati
  4. North Jakarta KPKP is Intensively Monitoring Animal Health Service Licensing

    access_time16-07-2026 remove_red_eye798 personAnita Karyati
  5. SDN Srengseng Sawah 15 Continues Face-to-Face Learning

    access_time13-07-2026 remove_red_eye717 personDessy Suciati