 3000 Meter Kubik Lumpur Berhasil Diangkut dari Kali Grogol, Palmerah

3,000 Cubic Meters of Mud Transported from Kali Grogol River

The West Jakarta Water Resources (SDA) Sub-agency has started dredging the Kali Grogol River, Palmerah. So far, they have collected around 3,000 cubic meters of mud.

Previously the mud had a thickness of about 6,000-7,000 cubic meter

Drainage Maintenance Division Head, Wawan Kurniawan said, it has been conducted since May 12 and was targeted to be complete in the upcoming August.

"Previously the mud had a thickness of about 6,000-7,000 cubic meter," he expressed, Wednesday (7/21).

PPSU Cleans Up Channel on Jalan Malaka Munjul

He said it was dredged up to one kilometer with six meters width using an amphibious excavator.

It was carried out in the morning until the afternoon. Afterwards, the mud collected on the riverbank and then transported at night using a dump truck and dumped into Ancol area, North Jakarta.

"We also coordinate with the local regional apparatus where the work is done at night without any problems, especially to transport the mud," he stated.

Linked News
Popular News indeks
  1. Transjakarta Resumes Operations with Strategic Service Adjustments

    access_time28-08-2026 remove_red_eye852 personAldi Geri Lumban Tobing
  2. Jakarta Deploys 120 Personnel to Counteract Traffic Disruption for Today’s Protests

    access_time27-08-2026 remove_red_eye793 personAldi Geri Lumban Tobing
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye770 personBudhi Firmansyah Surapati
  4. JIF Summit 2026 Drives Global Partnerships and Investment Growth in Jakarta

    access_time28-08-2026 remove_red_eye624 personAldi Geri Lumban Tobing
  5. Drainage Normalization on Jalan Mandioli to Be Completed in October

    access_time28-08-2026 remove_red_eye464 personFolmer