 3000 Meter Kubik Lumpur Berhasil Diangkut dari Kali Grogol, Palmerah

3,000 Cubic Meters of Mud Transported from Kali Grogol River

The West Jakarta Water Resources (SDA) Sub-agency has started dredging the Kali Grogol River, Palmerah. So far, they have collected around 3,000 cubic meters of mud.

Previously the mud had a thickness of about 6,000-7,000 cubic meter

Drainage Maintenance Division Head, Wawan Kurniawan said, it has been conducted since May 12 and was targeted to be complete in the upcoming August.

"Previously the mud had a thickness of about 6,000-7,000 cubic meter," he expressed, Wednesday (7/21).

PPSU Cleans Up Channel on Jalan Malaka Munjul

He said it was dredged up to one kilometer with six meters width using an amphibious excavator.

It was carried out in the morning until the afternoon. Afterwards, the mud collected on the riverbank and then transported at night using a dump truck and dumped into Ancol area, North Jakarta.

"We also coordinate with the local regional apparatus where the work is done at night without any problems, especially to transport the mud," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1623 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1457 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1321 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1095 personDessy Suciati
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye981 personDessy Suciati