 3000 Meter Kubik Lumpur Berhasil Diangkut dari Kali Grogol, Palmerah

3,000 Cubic Meters of Mud Transported from Kali Grogol River

The West Jakarta Water Resources (SDA) Sub-agency has started dredging the Kali Grogol River, Palmerah. So far, they have collected around 3,000 cubic meters of mud.

Previously the mud had a thickness of about 6,000-7,000 cubic meter

Drainage Maintenance Division Head, Wawan Kurniawan said, it has been conducted since May 12 and was targeted to be complete in the upcoming August.

"Previously the mud had a thickness of about 6,000-7,000 cubic meter," he expressed, Wednesday (7/21).

PPSU Cleans Up Channel on Jalan Malaka Munjul

He said it was dredged up to one kilometer with six meters width using an amphibious excavator.

It was carried out in the morning until the afternoon. Afterwards, the mud collected on the riverbank and then transported at night using a dump truck and dumped into Ancol area, North Jakarta.

"We also coordinate with the local regional apparatus where the work is done at night without any problems, especially to transport the mud," he stated.

Linked News
Popular News indeks
  1. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye615 personAldi Geri Lumban Tobing
  2. JITEX 2026: Fostering a Global Trade and Investment Ecosystem

    access_time01-09-2026 remove_red_eye567 personAldi Geri Lumban Tobing
  3. Pramono Confirms Permanent Bridge to Be Built in Tegal Alur

    access_time29-08-2026 remove_red_eye463 personDessy Suciati
  4. Jakarta Fine Arts and Ceramics Museum Hosts Malangan Exhibition

    access_time29-08-2026 remove_red_eye461 personFakhrizal Fakhri
  5. Pramono Emphasizes Importance of Creative Spaces for Children

    access_time03-09-2026 remove_red_eye438 personDessy Suciati