Pembangunan Jembatan Penyeberangan Sepeda Karet Sudirman Capai 67 Persen

Progress of Karet Sudirman Bicycle Crossing Bridge Construction has Reached 67 Percent

Progress of Karet Sudirman Bicycle Crossing Bridge (JPS) construction work which is located in front of Le Meredien Hotel has reached 67 percent.

All revitalization works are targeted to be completed and can be used by residents in November 2021

Jakarta Bina Marga Sub-agency Head, Hari Nugoho said, there were several works that have been completed, namely JPS foundation, elevator house foundation, strengthening existing JPO girder, and JPO ladder work.

His side is currently erecting JPS collumn/pole, installing lift house on the west side ( Le Meredien) and east side (Mayapada Tower), as well as production and preparation for JPS girder installation.

Traffic Engineering will Be Implemented Due to Sudirman Bicycle Crossing Bridge Construction

"In addition to crossing people, this bridge is also designed to support cyclists' mobility," he added, Monday (8/23).

He explained that there were several notes and corrections related JPS revitalization based on previous field observations, namely improving lightning especially in viewing the platform and strengthening existing crossing brisdge thus people can use it safely and comfortably.

"Karet Sudirman JPS will also be equipped with platform like Pinisi Ship. Besides, pedestrian bridge will be also equipped with CCTV, lightning, load sensors, and elevator for people with disabilities," he stated.

Karet Sudirman JPS, he continued, will be directly integrated with Transjakarta transportation modes. It will be also equipped with beautiful city lightning system to beautify the JPS at night.

"All revitalization works are targeted to be completed and can be used by residents in November 2021," he closed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1623 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1457 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1321 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1095 personDessy Suciati
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye981 personDessy Suciati