Normalisasi Saluran di Jalan Borobudur Capai 50 persen

Early February, Channel Normalization on Jalan Borobudur Completed

The channel normalization work on Jalan Borobudur, RT 11/02, Pegangsaan Urban Village, Menteng, Central Jakarta that is being carried out since November 2021 is targeted to be completed in early February 2022.

It has touched 50 percent or around 80 meters so far

Maintenance Division Head, Achmad Daeroby revealed, its normalization was carried out up to 170 meters length with 60 centimeters width and 70 centimeters width.

"It has touched 50 percent or around 80 meters so far. We do excavation again, as the previous channel that used concrete was damaged," he expressed, Monday (1/17).

Channel Normalization on Jalan Teuku Umar is Completed

He explained, it was aimed at following up on community reports complaining of flooding in front of Jalan Borobudur park, especially when it rains.

"The channel is built using U-ditch in a bid to smoothen and accommodate water in large quantities. To execute it, we involve around 15 personnel plus one mini excavator," he added.

Linked News
Popular News indeks
  1. Jakarta Provincial Government Receives a Grant of Rp 9.6 Billion in KPK`s Seized Assets

    access_time20-10-2026 remove_red_eye4538 personDessy Suciati
  2. Rano Reaffirms Jakarta's Vision of Becoming a City of Cinema

    access_time22-10-2026 remove_red_eye3596 personBudhi Firmansyah Surapati
  3. Drainage Channels Along Two Rawajati Roads Dredged

    access_time21-10-2026 remove_red_eye1735 personTiyo Surya Sakti
  4. Jakarta Pushed for Education Equity to Retain Top Student City Rank

    access_time19-10-2026 remove_red_eye979 personFakhrizal Fakhri
  5. Jakarta Esports 2026: Celebrating Local Games, Music and More

    access_time19-10-2026 remove_red_eye873 personAldi Geri Lumban Tobing