Pengurasan Saluran di Jalan Batang Hari Ditargetkan Rampung Akhir Januari

Channel Dredging Work on Jalan Batang Hari will Be Completed This Month

The channel dredging work which carried out since January 6 on Jalan Batang hari, RW 05, Cideng Urban Village, Gambir, Central Jakarta was targeted to finish by the end of this month.

Currently, we have dredged channel as long as 235 meters and transported 42.3 cubic meters mud

Gambir Sub-district Water Resources (SDA) Unit Head, Muhammad Imawan said, channel dredging progress has reached 66 percent or 235 meters of total length 355 meters.

"Currently, we have dredged channel as long as 235 meters and transported 42.3 cubic meters mud," he informed, Friday (1/21).

Water Channel on Jl. Prof. Dr. Satrio Dredged

According to him, it has width 60 centimeters and depth 70 centimeters with mud as thick as 40 centimeters.

"We deploy 10 personnel to dredge the channel," he mentioned.

Moreover, his side is also repairing damaged parts of channel along 7 meters. Personnel repair it manually using hoe, crowbar, shovel, plastic sack, and others.

"After being dredged, I hope residents can maintain its cleanliness," he stated.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1297 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1129 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye839 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye292 personAldi Geri Lumban Tobing
  5. Jakarta Speeds Up Flood Mitigation Efforts

    access_time08-03-2026 remove_red_eye288 personAldi Geri Lumban Tobing