Repair of Collapsed Sheet Pile on Jalan Nusa Indah Almost Complete

The Sulaeman connecting channel's 25-meter-long collapsed sheet pile, Jalan Nusa Indah, Cipinang Indah Housing Complex, RW 01 Cipinang Muara, Jatinegara, East Jakarta is still under repair or has reached 80 percent.

It is targeted to be completed within five days ahead

Jatinegara Sub-district Water Resources (SDA) Task Force Coordinator, Tamrizal said the repair was carried out with 25 meters in length, 120 centimeters in height, and 25 centimeters in width. It has been ongoing since a week ago.

"To repair, we have sent around 10 workers to the location," he expressed, Tuesday (3/1).

Damaged Roads in Pulogebang Being Repaired

He added the sheet pile collapsed after being eroded by water. The workers used river stones and installed a water pipe in the center of the sheet pile as flutes to absorb water.

"It is targeted to be complete within five days ahead," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1602 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1449 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1311 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1080 personDessy Suciati
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye973 personDessy Suciati