Perbaikan Turap Phb Sulaeman Capai 80 Persen

Repair of Collapsed Sheet Pile on Jalan Nusa Indah Almost Complete

The Sulaeman connecting channel's 25-meter-long collapsed sheet pile, Jalan Nusa Indah, Cipinang Indah Housing Complex, RW 01 Cipinang Muara, Jatinegara, East Jakarta is still under repair or has reached 80 percent.

It is targeted to be completed within five days ahead

Jatinegara Sub-district Water Resources (SDA) Task Force Coordinator, Tamrizal said the repair was carried out with 25 meters in length, 120 centimeters in height, and 25 centimeters in width. It has been ongoing since a week ago.

"To repair, we have sent around 10 workers to the location," he expressed, Tuesday (3/1).

Damaged Roads in Pulogebang Being Repaired

He added the sheet pile collapsed after being eroded by water. The workers used river stones and installed a water pipe in the center of the sheet pile as flutes to absorb water.

"It is targeted to be complete within five days ahead," he stated.

Linked News
Popular News indeks
  1. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1393 personNurito
  2. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye1026 personAldi Geri Lumban Tobing
  3. Kultura Market in Pademangan Barat Attracts Crowds

    access_time22-05-2026 remove_red_eye944 personAnita Karyati
  4. Inundation on DI Panjaitan Road Recede

    access_time20-05-2026 remove_red_eye855 personNurito
  5. Dharma Jaya Ready for Thousands of Eid al-Adha Sacrifices

    access_time20-05-2026 remove_red_eye671 personAldi Geri Lumban Tobing