Repair of Collapsed Sheet Pile on Jalan Nusa Indah Almost Complete

The Sulaeman connecting channel's 25-meter-long collapsed sheet pile, Jalan Nusa Indah, Cipinang Indah Housing Complex, RW 01 Cipinang Muara, Jatinegara, East Jakarta is still under repair or has reached 80 percent.

It is targeted to be completed within five days ahead

Jatinegara Sub-district Water Resources (SDA) Task Force Coordinator, Tamrizal said the repair was carried out with 25 meters in length, 120 centimeters in height, and 25 centimeters in width. It has been ongoing since a week ago.

"To repair, we have sent around 10 workers to the location," he expressed, Tuesday (3/1).

Damaged Roads in Pulogebang Being Repaired

He added the sheet pile collapsed after being eroded by water. The workers used river stones and installed a water pipe in the center of the sheet pile as flutes to absorb water.

"It is targeted to be complete within five days ahead," he stated.

Linked News
Popular News indeks
  1. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye945 personNurito
  2. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye621 personDessy Suciati
  3. Governor Attends Melasti Ceremony at Segara Temple

    access_time15-03-2026 remove_red_eye583 personBudhi Firmansyah Surapati
  4. Homecoming Travelers Surge Seen at Tanjung Priok Terminal

    access_time17-03-2026 remove_red_eye410 personAnita Karyati
  5. 24,412 Homecoming Travelers Departed from Senen Station

    access_time17-03-2026 remove_red_eye387 personFolmer