The West Jakarta Water Resources (SDA) Sub-agency accelerates the collapsed Citra 2 Connecting (Phb) Channel's retaining wall as high as 355 centimeters on Jalan Citra 2 Extention, Pegadungan Urban Village, Kalideres Sub-district.
The progress so far has only reached about 30 percent
West Jakarta SDA Sub-agency's Maintenance Section Head Wawan said the retaining wall was collapsed along 65 meters on the left side and 90 meters on the right side.
Repair of Collapsed Sheet Pile on Jalan Nusa Indah Almost Complete"We're currently repairing the left side that collapsed as long as 65 meters. It will be completed in the next two weeks," he stated, Wednesday (3/16).
His side deployed 15 personnel and one unit mini excavator to make repairs by installing 30-centimeters river stones, which have been carried out since March 3.
"The progress so far has only reached about 30 percent," he closed.