Normalisasi di Jalan Kebon Kacang 31 Telah Rampung

Micro Channel on Jalan Kebon Kacang 31 Normalized

The 70-meter-long micro water channel on Jalan Kebon Kacang 31, RW 04 Kebon Kacang Urban Village has been normalized.

It is carried out from February 21 and completed on March 29

Tanah Abang Sub-district Executing Unit Head Eli Menawan Sari said the normalization was done by increasing the width of the channel from 30 to 40 centimeters to accommodate water in large quantities.

"It is carried out from February 21 and completed on March 29," she explained, Monday (4/4).

Cilandak SDA Normalizes Pinang Kalijati Connecting Channel

According to her, the work that involved six workers plus a breaker and a generator was conducted manually starting from draining and installing the channel's sheet pile wall.

After it was completed, residents were expected to maintain cleanliness by not littering into the channel.

"Right now, our workers are seen completing the repair of the channel on Jalan Kebon Kacang 38 whose physical work is still 50 percent," she closed.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1098 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye581 personDessy Suciati
  3. Jakarta Steps Up to the Plate as PON 2028’s Support System

    access_time24-06-2026 remove_red_eye538 personFakhrizal Fakhri
  4. Jakarta Light Festival Dazzles Visitors at Kota Tua

    access_time22-06-2026 remove_red_eye512 personBudhi Firmansyah Surapati
  5. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye508 personNurito