Normalisasi Saluran Air di Jl Suci mencapai 80 Persen

Channel Normalization on Jalan Suci Reaches 80 Percent

The progress of channel normalization on Jalan Suci, RT 02/07 Susukan Urban Village, Ciracas, East Jakarta which has been carried out since early March has now reached 80 percent.

We target to finish it within 50 days

Ciracas Sub-district Water Resources (SDA) Executing Unit Head, Yulia Indah said it was done to follow up on the residents' proposals in the 2022 Musrenbang.

"The work that involves around 13 workers has been ongoing since March," she expressed, Monday (4/14).

Channels on Panggang Island Normalized

According to her, the channel with dimensions of 50x50 centimeters was normalized by using river stone material to make it wider to prevent puddles.

Thus far, the workers are seen installing a manhole cover using prefabricated concrete, as well as smoothing the bottom of the channel using river stones.

"We target to finish it within 50 days," she concluded.

Linked News
Popular News indeks
  1. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1208 personFolmer
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1193 personDessy Suciati
  3. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1179 personAldi Geri Lumban Tobing
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1053 personNurito
  5. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye988 personFolmer