Ini Progres Pekerjaan Konstruksi MRT Jakarta Fase 2A CP201

Here is Progress of Jakarta MRT Construction Work Phase 2A CP201

The construction work of the MRT Jakarta Phase 2A CP201 (Bundaran HI - Harmoni) which consists of Monas and Thamrin stations has entered the construction stage at the entrance area.

On behalf of MRT Jakarta, we apologize for any inconvenience during this work

The first gate to be built is Entrance - 1 Monas MRT Station, which is located on Jalan Museum and Jalan Medan Merdeka Barat.

PT MRT Jakarta's Corporate Secretary Division Head Rendi Alhial said that the construction of the entrance area used the box jacking method, which is a construction method for making underground tunnels through the process of pushing precast boxes segment by segment into the ground using a hydraulic jack.

DTKJ Hopes Jakarta LRT Can Increase Collaboration

As one of the stages of preparation for the construction work of Monas Station Entrance-1, test pit work would be executed at five points to identify and confirm the exact position of several underground utility networks that intersect with Entrance-1 construction work, such as PLN electricity cables, fiber optics, and PAM water pipes.

"On behalf of MRT Jakarta, we apologize for any inconvenience during this work. We hope for understanding and cooperation from the community to continuously support this project," he explained, Friday (8/19).

During the utility network test pit work, there will be a narrowing of the lane at some points on Jalan Museum:

1. August 18 to September 7, 2022

- MNS TP-22 and TP-25 test pits on Jalan Museum and inside the National Museum building area, there will be a narrowing of Jalan Museum lane in the test pit area

2. September 8 to 30, 2022

- MNS TP-23 and TP-24 test pits on Jalan Museum and inside the Kemenkominfo building area, there will be a narrowing of the Museum Road lane in this area

3. September 26 to October 29, 2022

- MNS TP-21 test pit, located in the median of Jalan Merdeka Barat, and has no impact on traffic along Jalan Medan Merdeka Barat

“We hope that road users can adjust to the diversions, obey the traffic signs and instructions from officers and prioritize road safety,” he stated.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1741 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1424 personFakhrizal Fakhri
  3. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1047 personBudhi Firmansyah Surapati
  4. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye962 personNurito
  5. Cake Making Training Held on Panggang Island

    access_time17-07-2026 remove_red_eye871 personAnita Karyati