Pengurasan Saluran di Jl. Kemanggisan Ilir Rampung Pekan Depan

This Week, Channel Dredging in Kemanggisan Ilir Completed

Thus far, around four cubic meters of mud have been picked up

The dredging project on the water channel on Jalan Kemanggisan Ilir, Kemanggisan Urban Village, Palmerah, West Jakarta that has been conducted since August 11 is targeted to be completed this week.

Palmerah Sub-district Water Resources Executing Unit Head Arif Junaidi said the channel has 150 meters in length, 40 centimeters in width, and 80 centimeters in height. Then the mud sedimentation in the channel reached 40 centimeters.

Dredging and Construction of Three Reservoirs in East Jakarta Accelerated

"Thus far, around four cubic meters of mud have been picked up and then disposed to the Ancol PLTU, North Jakarta," he said, Monday (8/22).

He explained that it was conducted to maximally accommodate rainwater when it rains and minimize inundation around the location.

"To finish it, we have sent around 12 workers to the location," he stated.

Linked News
Popular News indeks
  1. Pramono Flags Off 10,000 Runners at Soekarno Run 2026

    access_time15-02-2026 remove_red_eye1059 personFolmer
  2. Jakarta Unveils Indonesia’s First SDGs Corner at Maritime Museum

    access_time15-02-2026 remove_red_eye994 personNurito
  3. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye966 personAldi Geri Lumban Tobing
  4. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye928 personAldi Geri Lumban Tobing
  5. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye707 personAldi Geri Lumban Tobing