Next Week, Connecting Channel Dredging on Jalan Pekojan Completed

The work progress has touched 60 percent and is predicted to the completion on November 15

The connecting channel dredging work on Jalan Pekojan II, Gg. 4, RT 06/06 Pekojan Urban Village, Tambora, West Jakarta which has been conducted since November 2 is targeted to be completed next week.

Tambora Sub-district Water Resources (SDA) Executing Unit Head, Agus Purwanto said the channel that has 40 meters long, one meter wide, and 1.5 meters high is carried out manually by 10 workers.

Amarta: Ciliwung Sodetan Project will Be Completed Under Heru Leadership

"Thus far, the work progress has touched 60 percent and is predicted to the completion on November 15," he expressed, Tuesday (11/8).

He added that it is carried out by opening the concrete slab, then dredging the mud to 25 to 30 centimeters deep.

"After it is done, the channel can accommodate water maximally in order to minimize flooding when it rains," he stated.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1452 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1173 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye982 personFolmer
  4. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye885 personAldi Geri Lumban Tobing
  5. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye853 personAldi Geri Lumban Tobing