Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen
....
photo Anita Karyati - Beritajakarta.id

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1036 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye902 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye544 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye446 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye379 personAldi Geri Lumban Tobing