Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye394 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close