Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. May Day: Transjakarta Service Adjustments

    access_time01-05-2026 remove_red_eye818 personAldi Geri Lumban Tobing
  2. Dinkes Sets Up Health Posts for May Day Events

    access_time01-05-2026 remove_red_eye567 personDessy Suciati
  3. The Lights-Out Action Successfully Reduces Carbon Emissions

    access_time27-04-2026 remove_red_eye562 personAldi Geri Lumban Tobing
  4. City Deploys Massive Cleanup Force for May Day at Monas

    access_time01-05-2026 remove_red_eye560 personAldi Geri Lumban Tobing
  5. MRT Jakarta Urged to Enhance Power Outage Mitigation System

    access_time27-04-2026 remove_red_eye547 personFakhrizal Fakhri