Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye708 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye668 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye666 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye633 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye629 personAldi Geri Lumban Tobing