Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye518 personDessy Suciati
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye514 personAldi Geri Lumban Tobing
  3. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye494 personFolmer
  4. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye489 personNurito
  5. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye481 personAldi Geri Lumban Tobing