Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye832 personTiyo Surya Sakti
  2. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye768 personNurito
  3. Posyandu-Posbindu Services Reach 1,600 Seniors and Toddlers in Utan Panjang

    access_time07-04-2026 remove_red_eye729 personFolmer
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye673 personTiyo Surya Sakti
  5. West Jakarta BPN Holds Mobile Land Service in Kembangan

    access_time06-04-2026 remove_red_eye617 personBudhi Firmansyah Surapati