Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Jakarta Set to Launch Historic Municipal Bonds, Pramono Says

    access_time01-07-2026 remove_red_eye1133 personDessy Suciati
  2. Jakarta Government Quickly Addresses Toddler Falling into a Hole Incident

    access_time29-06-2026 remove_red_eye651 personDessy Suciati
  3. Jakarta Primed for Transformation into a World-Class Global Hub

    access_time28-06-2026 remove_red_eye651 personDessy Suciati
  4. Central Jakarta Offers Free Tattoo Removal Service to 100 Residents

    access_time29-06-2026 remove_red_eye511 personFolmer
  5. Asylum Seekers Urged Not to Occupy Public Facilities Outside UNHCR Office

    access_time02-07-2026 remove_red_eye487 personTiyo Surya Sakti