Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Pramono Ready to Beautify Jakarta as Requested by President

    access_time03-02-2026 remove_red_eye1146 personDessy Suciati
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye902 personTiyo Surya Sakti
  3. Coastal Children Enthusiastic Over Betawi Dance Training at Arung Palaka Hub

    access_time02-02-2026 remove_red_eye855 personAnita Karyati
  4. 782 Pets in South Jakarta Receive Anti-rabies Vaccine

    access_time03-02-2026 remove_red_eye565 personTiyo Surya Sakti
  5. BPS Reports Jakarta Experienced 0.23 Percent Deflation in January 2026

    access_time02-02-2026 remove_red_eye494 personFolmer