Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Jakarta's Central Statistics Agency Records Inflation at 0.63 Percent

    access_time02-03-2026 remove_red_eye851 personFolmer
  2. Liquor Raids in East Jakarta Continue to Be Intensified

    access_time02-03-2026 remove_red_eye631 personNurito
  3. Pramono Calls on Mudik Travelers to Notify Local Officials

    access_time27-02-2026 remove_red_eye531 personDessy Suciati
  4. Pramono: Jakarta Ready to Pay Out Holiday Bonus to ASN

    access_time04-03-2026 remove_red_eye526 personDessy Suciati
  5. Free Homecoming 2026 Program Draws Strong Interest from N. Jakarta Residents

    access_time27-02-2026 remove_red_eye470 personAnita Karyati