Revitalisasi Jembatan Cinta Pulau Tidung Tahap II Capai 30 Persen

Revitalization of Tidung Island Cinta Bridge Resumes

The Seribu Islands Technical Work Unit (UKT) 2 is continuing the second phase of the Tidung Island Cinta 'Love' Bridge revitalization, South Seribu Islands.

The progress so far has touched 30 percent

Seribu Islands UKT City Lighting Division Head, Wibi Abdi said the second revitalization has been ongoing since early July 2023 and has touched 480 meters long. Then the first phase was completed in 2022 with 200 meters long.

"The progress so far has touched 30 percent, covering installation of 415 piles, fabrication, gesting and ironing," he said, Monday (7/31).

Cinta Bridge Revitalization on Tidung Island Resumed

In early August, the work would enter casting phase. Eventually, the brige would have a Sea Water Reverse Osmosis (SWRO) dan a water dance.

"It will take six months or complete in the end of this year," he expressed.

He asserted his party will keep monitoring it for optimal results.

"We'll continue to present the latest concepts, thus residents and tourists can enjoy it," he closed.

Linked News
Popular News indeks
  1. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye1100 personAldi Geri Lumban Tobing
  2. Pademangan Health Center Promotes 3M Plus to Prevent Dengue Fever

    access_time14-04-2026 remove_red_eye816 personAnita Karyati
  3. Jakarta Provincial Government Fully Supports BTN JAKIM 2026

    access_time14-04-2026 remove_red_eye727 personDessy Suciati
  4. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye691 personFakhrizal Fakhri
  5. Jakarta Regional Budget Spending Reaches Rp10.38 Trillion in Q1

    access_time17-04-2026 remove_red_eye640 personDessy Suciati