Eigth personnel of the Kramat Jati Water Resources (SDA) Task Force, East Jakarta has started to repair the collapsed sheet pile of the crossing channel on Jalan Al Hidayah, RT 01/03 Cililitan Urban Village. The repair has been carried out since Monday (10/9).

It is targeted for completion next week

Kramat Jati Sub-district SDA Executing Unit Head, Muklis expressed the collapse was occurred up to six meters and 2.1 meters. Even at the sheet pile, there was a gaping hole three meters long and two meters deep.

"The repair is done manually. The work progress has touched 20 percent so far. It is targeted for completion next week," he said, Thursday (10/12).

Channel in Cempaka Putih Timur Repaired

He explained the channel along Jalan Swadaya is an access link for the residential area of RT 01/03 Cililitan to Jalan Raya Cililitan Besar or to PGC.

Previously, residents built this place independently in 1986. It was right behind the Environmental Agency office and flanked on the east side by the Jagorawi Toll Road.

"We repair it using river stones to get solid results," he stated.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1100 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye583 personDessy Suciati
  3. Jakarta Steps Up to the Plate as PON 2028’s Support System

    access_time24-06-2026 remove_red_eye540 personFakhrizal Fakhri
  4. Jakarta Light Festival Dazzles Visitors at Kota Tua

    access_time22-06-2026 remove_red_eye517 personBudhi Firmansyah Surapati
  5. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye511 personNurito