Crossing Channel on Jalan Jambore Cibubur Begins Installation

The 13-meter-long water channel crossing on Jalan Raya Jambore, Cibubur, Ciracas, East Jakarta has begun to be installed. The crossing uses a 1.2-meter box culvert and is planted at a depth of 1.2 meters. It has been ongoing in stages from Thursday (10/24) to Friday (10/25) night.

We installed the initial six meter box culvert last night until this morning

East Jakarta Water Resources (SDA)'s Developement and Drainage Improvement Section Head, Tengku Saugi Zikri, said the initial stage of installing the box culvert started from the west side of Jalan Jambore, along six meters. The work was conducted from 9 PM to 5 AM.

"We installed the initial six meter box culvert last night until this morning. Later that evening the second stage will continue for seven meters," he expressed, Friday (10/25)

Channel Crossing Construction on Jalan Lebak Lestari Indah Completed

He explained after the box culvert was installed directly above it was covered using steel plates. Thus, during the day the road can be crossed by vehicles considering the area is quite busy with motorists because this road connects East Jakarta with Depok and Bekasi.

According to him, this crossing is part of a water channel construction project using the jacking method. Its installation was conducted at the lowest point on the road which is often flooded during rain with a height of 40 to 80 centimeters.

"Later, flooding on the road can go straight into the crossing and flow into the channel with a jacking system until they finally flow into the Rawa Dongkal Reservoir," he explained.

He added the length of the jacking pipe to be installed is 370 meters, the point starts from the bend near the steel shop to SMPN 147. The material used is 150x150x120 centimeter U-Ditch concrete, 120x110x100 centimeter box culvert, 80x80x120 centimeter U-Ditch.

On Jalan Jambore, four diversion points would be excavated and on Jalan SMPN 147 there were two points. The land excavation for the installation of U-Ditch and box culvert varies in size 4x6 meters and 4x6.68 meters with a depth of between 3.86 meters to 6.48 meters.

According to the work contract, the implementation will be executed by a third party from July 18 to November 29 or 125 working days.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1454 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1203 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye983 personFolmer
  4. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye941 personAldi Geri Lumban Tobing
  5. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye886 personAldi Geri Lumban Tobing