Personel SDA menormalisasi saluran air di Jalan Kramat Lontar

Kramat Lontar Gang 10 Drainage Work 60 Percent Complete

Drainage normalization project in residential area of Jakan Kramat Lontar Gang 10, RW 01, Paseban Urban Village, Senen, has reached over 60 percent completion. The project, carried out by Central Jakarta Water Resources (SDA) Sub-agency since July, is progressing steadily.

"We aim to complete the work by October 15,"

Damaged Retaining Wall in Kelapa Gading Timur Being Repaired

Senen Sub-district SDA Unit Head, Zulfahmi, mentioned that the 270-meter-long drainage is being normalized by installing 40x60 centimeters U-ditch concrete channels.

"So far, we've completed 180 meters, or approximately 66.6 percent of the total length," said Zulfahmi on Thursday (10/2).

According to him, the project was proposed by residents through Rembuk RW and included in the 2024 Musrenbang.

"We aim to complete the work by October 15," he added.

The project received positive feedback from Bambang (43), a local resident, who said the old drainage was too narrow to handle heavy rainfall.

"Hopefully, the work finishes soon so we won't have to worry about flooding during peak rainy season," he expressed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye414 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close