Channel Dredging on Jl Gelinggang to Complete End of October

The progress has reached 25 percent

Central Jakarta Water Resources Sub-agency is about to complete water channel renovation on Jalan Gelinggang C3 RT 11/04, Bendungan Hilir, Tanah Abang, this month.

Collapsed Retaining Wall on Jalan Batu Tumbuh Being Repaired

Head of Tanah Abang District's Water Resource Unit, Eli Menawan Sari said the renovation along 125 meters has been running since last week. Now the progress reaches 25 percent.

"The progress has reached 25 percent and is targeted for completion at the end of October," she said, Thursday (10/9).

Renovation is run because the channel made of PVC pipe was damaged, so it was no longer able to accommodate the water during rain.

"We install new u-ditches by 60x60 cm of size," she added.

Meanwhile, Head of Bendungan Hilir Urban Village, Rida Mufrida, appreciated the sub-agency's response in renovating the water channel.

"We submitted proposal to follow up residents' request for renovating the channel," she admitted.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye792 personAldi Geri Lumban Tobing
  2. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye588 personNurito
  3. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye566 personFakhrizal Fakhri
  4. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye555 personBudhi Firmansyah Surapati
  5. PT JIEP Targets Shenzhen Businesses with Investment Offers

    access_time24-04-2026 remove_red_eye548 personAldi Geri Lumban Tobing