Proses perbaikan Saluran Penghubung yang Ambrol di Jalan Petamburan IV

Phb Drainage Repair on Jalan Petamburan IV to Wrap Up by Year's End

Repair work on a collapsed section of the connecting (Phb) drainage wall on Jalan Petamburan IV is targeted for completion by the end of December.

"We're aiming to complete the repairs within 15 working days,"

Central Jakarta Water Resources (SDA) Sub-agency Drainage Maintenance Section Head, Citrin Indriati, said that 15 blue troops personnel have been repairing the 10-meter-long collapsed wall since Monday (12/15).

Channel on Jalan Manggis II Being Normalized

"We're aiming to complete the repairs within 15 working days, or by the end of December," she stated on Tuesday (12/16).

To prevent further damage, she added, her team is using river stones to rebuild the drainage wall.

Meanwhile, Yudi (39), a resident of RT 09/RW 05, Petamburan Urban Village, appreciated the swift response from the Central Jakarta SDA Sub-agency in following up on the residents' report via Jakarta Kini (JaKi) app.

"Thank you for the quick response in repairing the Phb channel. We don't have to worry anymore about the wall collapsing again," he expressed.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1769 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1508 personFakhrizal Fakhri
  3. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1103 personFakhrizal Fakhri
  4. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1091 personBudhi Firmansyah Surapati
  5. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye999 personNurito