You don't have javascript enabled. Good luck with that.
Pencarian
Proses perbaikan Saluran Penghubung yang Ambrol di Jalan Petamburan IV

Phb Drainage Repair on Jalan Petamburan IV to Wrap Up by Year's End

Repair work on a collapsed section of the connecting (Phb) drainage wall on Jalan Petamburan IV is targeted for completion by the end of December.

"We're aiming to complete the repairs within 15 working days,"

Central Jakarta Water Resources (SDA) Sub-agency Drainage Maintenance Section Head, Citrin Indriati, said that 15 blue troops personnel have been repairing the 10-meter-long collapsed wall since Monday (12/15).

Channel on Jalan Manggis II Being Normalized

"We're aiming to complete the repairs within 15 working days, or by the end of December," she stated on Tuesday (12/16).

To prevent further damage, she added, her team is using river stones to rebuild the drainage wall.

Meanwhile, Yudi (39), a resident of RT 09/RW 05, Petamburan Urban Village, appreciated the swift response from the Central Jakarta SDA Sub-agency in following up on the residents' report via Jakarta Kini (JaKi) app.

"Thank you for the quick response in repairing the Phb channel. We don't have to worry anymore about the wall collapsing again," he expressed.

Linked News
Popular News indeks
  1. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye673 personNurito
  2. Governor Attends Melasti Ceremony at Segara Temple

    access_time15-03-2026 remove_red_eye560 personBudhi Firmansyah Surapati
  3. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye414 personDessy Suciati
  4. Travelers Departing from Lebak Bulus Terminal Starting to Increase

    access_time13-03-2026 remove_red_eye312 personTiyo Surya Sakti
  5. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye308 personAldi Geri Lumban Tobing