Saluran Air di Jalan Kebon Kacang 43 Dinormalisasi

Kebon Kacang 43 Drainage Project Slated for Late February Finish

A 170-meter drainage upgrade on Jalan Kebon Kacang 43 is in the pipeline for a late February finish. Tanah Abang’s Water Resources (SDA) Head, Eli Menawan Sari confirmed that the eight-person team is working around the clock to install concrete drainage units.

We’ve been at it since January 12

"We’ve been at it since January 12 and aim to cross the finish line by the end of next month," she expressed, Tuesday (1/20).

The project, which utilizes 40x40 cm precast concrete drains, is on track to be finished by late February.

Jakarta Govt Extends Weather Modification Operations Amid Flood Concerns

Agus (36), a local resident, gave a thumbs up to the project, noting it was a direct follow-up from a Jakarta City Council member’s recess.

"I hope this upgrade puts an end to the overflows that frequently cause flooding in our area," he stated.

Linked News
Popular News indeks
  1. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1309 personAldi Geri Lumban Tobing
  2. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye1223 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye1036 personFolmer
  4. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye962 personDessy Suciati
  5. Pram Inaugurates Matraman Health Center, Calls for Seamless Public Service

    access_time05-06-2026 remove_red_eye793 personDessy Suciati