The South Jakarta Sub-dept. of Water Management began to dredge sediment in Krukut River, Petogogan Urban Village, South Jakarta as rainy season anticipation.

The dredging was done along 200 meters width and two meters depth

About 500 tons of sediment were transported from the river since Monday (7/27) to Thursday (7/30).

"The dredging was done along 200 meters width and two meters depth," said Suyadi, Head Section of Flood Control System Maintenance for South Jakarta Water Management Sub-department, Friday (7/31).

2 Excavators Sent to Krukut River as Flood Anticipation

Relaying on beritajakarta.com observation, there were two excavators deployed to dredge the sediment.

"Our target is dredging 1,500 meters within 1.5 months. The dry sediment will be transported to Ancol coal fired power plant (PLTU) area," he disclosed.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1585 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1438 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1302 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1095 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye966 personDessy Suciati