Jalan Layang Ciledug-Tendean Rampung 17 Persen

CIledug-Tendean Flyover Project 17 Percent Complete

The construction of a flyover for Transjakarta bus lane plying corridor XII (Ciledug-Kapten P Tendean) has reached 17 percent. It is beyond determined target that was about 14 percent. 

Currently, it's been 17 percent, and beyond our target that was 14 percent

The project is divided into 8 packets. The construction of the 9,3-kilometer flyover would take 661 days starting from February 2015 and targeted to be complete in December 2016. 

"Currently, it's been 17 percent, and beyond our target that was 14 percent," said Head of Jakarta Bina Marga's Overpass and Intersection Department, Heru Suwondo, Tuesday (8/11). 

Congestion Along Ciledug-Tendean Getting Worse

Regarding traffic congestion caused by the project, Suwondo claimed, he will try maximally to anticipate it by coordinating with police and Jakarta Transportation Department. 

He also promises to re-function damaged roads and sidewalks due to the project, as before. 

"The roads and sidewalks will eventually be functioned as before. For instance, if there are formerly 2 lanes, they would keep being like that, as well as sidewalks for pedestrians," he explained.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2430 personTiyo Surya Sakti
  2. Fire at Pondok Bambu Allegedly Triggered by Electrical Short

    access_time19-05-2026 remove_red_eye1347 personNurito
  3. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1158 personAldi Geri Lumban Tobing
  4. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye978 personAldi Geri Lumban Tobing
  5. Pramono: Jakarta Remains the Capital City Until a Presidential Decree Is Issued

    access_time13-05-2026 remove_red_eye954 personDessy Suciati