September, Infrastruktur Terminal Pulogebang Rampung

December, Terminal Pulogebang Officially Operated

Preparation for Pulogebang Terminal Operational as Inter-City Inter-Provincial (AKAP) Integrated Terminal keeps being accelerated. As planned, the terminal as wide as 14 hectares will be functioned by the end of 2015. 

Predictably, terminal could already be inaugurated in September or December

At this time, the readiness of terminal infrastructure and facility has reached 99 percent, and only leaves about 100 meters of highway access.

Head of Pulogebang Terminal Services Partnership, Iwa Kartiwa said the Bina Marga Department will complete the rest work in the upcoming September. Meanwhile, the operational license type A is still under process.

Pulogebang Terminal Becomes Free Homecoming Locations

"The license was already filed to Transportation Department in early June," he told, Thursday (8/13).

He told, he was optimistic terminal can be operated at the end of 2015 because almost requirements as terminal type A can be met.

"Predictably, terminal could already be inaugurated in September or December. Some of the buses are already operating now," he uttered.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye772 personAldi Geri Lumban Tobing
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye657 personTiyo Surya Sakti
  3. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye558 personNurito
  4. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye546 personFakhrizal Fakhri
  5. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye544 personBudhi Firmansyah Surapati