Normalisasi Sisi Timur Situ Rawa Badung Capai 20 Persen

Normalization of Rawa Badung Dam Has Reached 20 Percent

The revitalization project of Rawa Badung Dam's east side, Jatinegara Urban Village, Cakung Sub-District, keeps being accelerated. Until this time, its process has reached 20 percent. 

Now it's already shaped. Around the project has been fenced

The dam which was previously full of buildings, will be dredged to be refunctioned. Predictably, 36,000 cubic out of 2.5 hectares land area will be dredged with 2 m depth. 

Head of Water Resource Maintenance Section for East Jakarta Water Management Sub-Department, Mukhid stated the project has finalized most of land. To keep it being occupied and as a project safety, the area has been fenced. 

Channel in C. Jakarta Mayor Office Normalized

"Now, it's already shaped. Around the project has been fenced," he told, Wednesday (9/23). 

He uttered, to reach the revitalization target, the project is conducted at night and day. Every day, there are at least 3 heavy equipments sent to the field. 

"It is targeted to be complete in the upcoming December. We hope the dam could minimize puddles on Jalan KRT Radjiman and its surrounding areas in future," he closed. 

Linked News
Popular News indeks
  1. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye628 personBudhi Firmansyah Surapati
  2. Road to Larata Run 2026 Combines Running with Public Transport

    access_time31-10-2026 remove_red_eye551 personAnita Karyati
  3. Faith Meets Progress, Ancol Prayer Gathering Fortifies Jakarta’s Journey as a Global City

    access_time01-11-2026 remove_red_eye384 personAnita Karyati
  4. House Fire in Sunter Agung Successfully Extinguished

    access_time04-11-2026 remove_red_eye380 personAnita Karyati
  5. Brunei Darussalam Delegation Invited to Explore Jakarta`s Marine Tourism Destinations

    access_time02-11-2026 remove_red_eye347 personAldi Geri Lumban Tobing