Terhambat Lelang, Pengerukan Waduk Belum Optimal
.
photo istimewa - Beritajakarta.id

Late Auction, Reservoir Dredging Unoptimal

The reservoir dredging and connecting channel project in West Jakarta is unoptimal. It only reached 20 percent.

Connecting channel total in West Jakarta are 314 points

Santo, West Jakarta Head Section of Flood Handling System Maintenance for Sub-dept. of Water Management, said the unoptimal dredging project is caused by late auction process in local Goods and Service Procurement Unit.

"Connecting channel total in West Jakarta are 314 points," he said.

Water Channel on Jalan Cilandak KKO Dredged

According to him, his side planned to normalize Rawabekel River in Cengkareng Barat and Semongol River in Kalideres.

As for the Rawabekel River, the depth will be added from 1.5 meters to 2.5 meters.

"Sheet pile will be installed first before the dredging," he added.

The same depth will also be applied for Semongol River.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1039 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye904 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye546 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye447 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye380 personAldi Geri Lumban Tobing