39 Muara Baru Dike Piles Have Been Installed

The construction of sea dike for stage 2 package 1 at Muara Baru, Penjaringan, North Jakarta is started. At this moment, 39 dike piles have been installed along 50 meters.

Piles installation can reach two or three spots. The installation also depends on weather condition

Agus Priyono, project implementer, said the dike will be constructed along 1.8 kilometers and targeted to completed in mid 2018.

“Piles installation can reach two or three spots. The installation also depends on weather condition,” he said, Thursday (9/15).

This Year, Sea Dike Pole Targeted to Be Installed in April 2018

He added that the pile has length by 24 meters and diameter is 1.2 meters. The pile is planted 17 meters under the sea and 3.5-4.5 meters above the sea.

He ensures the pile will be able to block tidal wave.

“It surely assist the surrounding residents,” he closed.

Linked News
Popular News indeks
  1. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye359 personTiyo Surya Sakti
  2. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye329 personAldi Geri Lumban Tobing
  3. Rano Inspects Location and Delivers Aid to Fire Victims in Bukit Duri

    access_time20-07-2025 remove_red_eye327 personNurito
  4. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye320 personAldi Geri Lumban Tobing
  5. Council Urges Free School Programs to Prioritize Principles of Fairness and Quality

    access_time18-07-2025 remove_red_eye317 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik