Pembangunan MRT Sudah Gunakan 40 Persen dari Dana Pagu
.
photo Reza Hapiz - Beritajakarta.id

MRT Has Spent 40 Percent of Its Budget

The construction of Mass Rapid Transit (MRT) has reached 60.22 percent. Total spent budget is Rp 4.63 trillion or 40 percent of its total budget.

Budget realization of MRT project reaches Rp 4.63 trillion

PT MRT Director, William P Sabandar, said total budget for MRT is Rp 11.69 trillion. The project has been started since 2013 ago.

“Budget realization of MRT project reaches Rp 4.63 trillion,” he said, Saturday (12/17).

Earthquake Resistance of MRT Building Is Up to 8.7 SR

According to him, this year budget for MRT was Rp 2.67 trillion. In fact, budget realization is predicted to reach 63 percent or Rp 1.63 trillion.

“Land buying process disturbed the budget realization,” he added.

He continued that the project has reached 60.22 percent. In details are 42.74 percent for flyover and 77.86 percent for underground constructions.

“We’ll accelerate the project next year. It is targeted to operate in February 2019,” he closed.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye471 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye412 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye324 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye285 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye271 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik