Pengerjaan MRT Bisa Selesai Tepat Waktu

MRT Project Can Finish On Time

Deputy Governor of Industry, Trade and Transportation, Sutanto Soehodho visited the Mass Rapid Transit (MRT) project at Bundaran Hotel Indonesia.

Solution can be provided to solve the land buying process. It can be temporarily postponed

There were also Deputy Governor of Spatial Planning and Environment Oswar Muadzin Mungkasa and several Assistant Deputy Governor. The visit was led by PT MRT Jakarta Director William Sabandar.

According to him, the tunnel is almost complete and needs rail, rolling stock, mechanical and electrical. The problem remains on land buying process for flyover.

MRT Has Spent 40 Percent of Its Budget

“Solution can be provided to solve the land buying process. It can be temporarily postponed,” he said.

Meanwhile, William Sabandar, explained that MRT project spends Rp 14.2 trillion with 13 stations. Bundaran HI-Lebak Bulus can be passed in 30 minutes.

“Elevated section progress has reached 42.74 percent and underground section is 77.87 percent. Total progress is 60.22 percent,” he stated.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2403 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye790 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  5. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye518 personNurito