MRT Project Can Finish On Time
access_time December 23 2016 03:14 PM remove_red_eye 1903
Reported by Jhon Syah Putra Kaban | Translated by Rizky Mawardi
Reported by Jhon Syah Putra Kaban | Translated by Rizky Mawardi
Deputy Governor of Industry, Trade and Transportation, Sutanto Soehodho visited the Mass Rapid Transit (MRT) project at Bundaran Hotel Indonesia.
Solution can be provided to solve the land buying process. It can be temporarily postponed
There were also Deputy Governor of Spatial Planning and Environment Oswar Muadzin Mungkasa and several Assistant Deputy Governor. The visit was led by PT MRT Jakarta Director William Sabandar.
According to him, the tunnel is almost complete and needs rail, rolling stock, mechanical and electrical. The problem remains on land buying process for flyover.
MRT Has Spent 40 Percent of Its Budget“Solution can be provided to solve the land buying process. It can be temporarily postponed,” he said.
Meanwhile, William Sabandar, explained that MRT project spends Rp 14.2 trillion with 13 stations. Bundaran HI-Lebak Bulus can be passed in 30 minutes.
“Elevated section progress has reached 42.74 percent and underground section is 77.87 percent. Total progress is 60.22 percent,” he stated.