Pembangunan Velodrome Capai 40 Persen
.
photo Reza Hapiz - Beritajakarta.id

Velodrome Construction Has Reached 40 Percent

The Velodrome bike racing construction in Rawamangun, East Jakarta has reached 40 percent. This achievement is faster four percent compared to a plan that has been set.

The construction has been ongoing since June 2016 and will be complete in June 2018

According to Iwan Takwin, Manager of Velodrome Venue Project for PT Jakarta Propertindo (Jakpro), the Velodrome project is using the concept of design and build. 

Sumarsono Optimistic Velodrome Construction Finish On Time

"The construction has been ongoing since June 2016 and will be complete in June 2018," he disclosed, when he accompanied the review conducted by Jakarta Governor, Basuki T. Purnama, Friday (2/24).

His party also has conducted innovations in anticipation of the weather factor. This is because, this month is predicted the peak of the rainy season.

"If the inundation occurs, we'll soon do pumping," he stated.

As known, the Rawamangun Velodrome is one of the venues that will be used in the arena of 2018 Asian Games.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1045 personAldi Geri Lumban Tobing
  2. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye908 personFolmer
  3. Legislator Ahmad Lukman Jupiter Wants PT FSTJ Add Shop Cars

    access_time19-11-2024 remove_red_eye553 personDessy Suciati
  4. PMPTSP Agency Launches PIN Greenvest to Prompt Green and Sustainable Investment

    access_time21-11-2024 remove_red_eye449 personAldi Geri Lumban Tobing
  5. Transjakarta Extends its Operation to 11 PM Today

    access_time19-11-2024 remove_red_eye386 personAldi Geri Lumban Tobing