Pembangunan Velodrome Capai 40 Persen

Velodrome Construction Has Reached 40 Percent

The Velodrome bike racing construction in Rawamangun, East Jakarta has reached 40 percent. This achievement is faster four percent compared to a plan that has been set.

The construction has been ongoing since June 2016 and will be complete in June 2018

According to Iwan Takwin, Manager of Velodrome Venue Project for PT Jakarta Propertindo (Jakpro), the Velodrome project is using the concept of design and build. 

Sumarsono Optimistic Velodrome Construction Finish On Time

"The construction has been ongoing since June 2016 and will be complete in June 2018," he disclosed, when he accompanied the review conducted by Jakarta Governor, Basuki T. Purnama, Friday (2/24).

His party also has conducted innovations in anticipation of the weather factor. This is because, this month is predicted the peak of the rainy season.

"If the inundation occurs, we'll soon do pumping," he stated.

As known, the Rawamangun Velodrome is one of the venues that will be used in the arena of 2018 Asian Games.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1106 personFakhrizal Fakhri
  2. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye995 personAldi Geri Lumban Tobing
  3. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye950 personAldi Geri Lumban Tobing
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye725 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye627 personAnita Karyati