You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Velodrome Capai 40 Persen
.
photo Reza Hapiz - Beritajakarta.id

Velodrome Construction Has Reached 40 Percent

The Velodrome bike racing construction in Rawamangun, East Jakarta has reached 40 percent. This achievement is faster four percent compared to a plan that has been set.

The construction has been ongoing since June 2016 and will be complete in June 2018

According to Iwan Takwin, Manager of Velodrome Venue Project for PT Jakarta Propertindo (Jakpro), the Velodrome project is using the concept of design and build. 

Sumarsono Optimistic Velodrome Construction Finish On Time

"The construction has been ongoing since June 2016 and will be complete in June 2018," he disclosed, when he accompanied the review conducted by Jakarta Governor, Basuki T. Purnama, Friday (2/24).

His party also has conducted innovations in anticipation of the weather factor. This is because, this month is predicted the peak of the rainy season.

"If the inundation occurs, we'll soon do pumping," he stated.

As known, the Rawamangun Velodrome is one of the venues that will be used in the arena of 2018 Asian Games.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye954 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye660 personBudhi Firmansyah Surapati
  3. Satpol PP Expels Illegal Participants at Sudirman - Thamrin CFD

    access_time27-10-2024 remove_red_eye454 personBudhi Firmansyah Surapati
  4. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye395 personTiyo Surya Sakti
  5. Traffic Arrangement Applied on Jalan Tambak

    access_time28-10-2024 remove_red_eye370 personAldi Geri Lumban Tobing