Pemasangan SGB di Depo LRT Kelapa Gading Dimulai

Segmental Girder Box Installation at Kelapa Gading LRT Begins

The first installation of the segmental girder box (SGB) at Light Rail Transit (LRT), Jalan Boulevard Utara, Kelapa Gading Timur, North Jakarta begins.

Launching gantry system is not using a crane car

PT Jakarta Propertindo (Jakpro) President Director, Satya Heragandhi said, until the end of this year, 1,300 SGBs are targeted to be installed at LRT lane as long as six kilometers, starting from Kelapa Gading Depot until Velodrome Rawamangan Station.

As the initial stage, he stated, 4 SGBs will be installed using launching gantry system.

LRT Construction Phase 1 Reaches 12.75 Percent

"Launching gantry system is not using a crane car. Once pulled up, it is directly assembled by the launcher," he expressed, Monday (5/29).

To speed up its installation, his side intends to prepare four units of launching gantry. Thus the project can be completed this year, and then continued with railway construction and train procurement in 2018.

"The pile is big enough and can withstand earthquakes with a magnitude of 5.2 on the Richter scale. Thus far the project has touched 21 percent," he closed.

Linked News
Popular News indeks
  1. East Jakarta Satpol PP Deployed to Ensure Safe Eid Travel Period

    access_time16-03-2026 remove_red_eye993 personNurito
  2. Car Free Night Held on Eid Eve, Be There!

    access_time19-03-2026 remove_red_eye661 personDessy Suciati
  3. Pramono Inaugurates 26 Home Renovation Units

    access_time16-03-2026 remove_red_eye656 personDessy Suciati
  4. Governor Attends Melasti Ceremony at Segara Temple

    access_time15-03-2026 remove_red_eye624 personBudhi Firmansyah Surapati
  5. Homecoming Travelers Surge Seen at Tanjung Priok Terminal

    access_time17-03-2026 remove_red_eye618 personAnita Karyati