The first installation of the segmental girder box (SGB) at Light Rail Transit (LRT), Jalan Boulevard Utara, Kelapa Gading Timur, North Jakarta begins.

Launching gantry system is not using a crane car

PT Jakarta Propertindo (Jakpro) President Director, Satya Heragandhi said, until the end of this year, 1,300 SGBs are targeted to be installed at LRT lane as long as six kilometers, starting from Kelapa Gading Depot until Velodrome Rawamangan Station.

As the initial stage, he stated, 4 SGBs will be installed using launching gantry system.

LRT Construction Phase 1 Reaches 12.75 Percent

"Launching gantry system is not using a crane car. Once pulled up, it is directly assembled by the launcher," he expressed, Monday (5/29).

To speed up its installation, his side intends to prepare four units of launching gantry. Thus the project can be completed this year, and then continued with railway construction and train procurement in 2018.

"The pile is big enough and can withstand earthquakes with a magnitude of 5.2 on the Richter scale. Thus far the project has touched 21 percent," he closed.

Linked News
Popular News indeks
  1. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye627 personDessy Suciati
  2. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye577 personTiyo Surya Sakti
  3. East Jakarta Red Cross Provides Aid to Utan Kayu Utara Fire Survivors

    access_time07-08-2026 remove_red_eye442 personNurito
  4. Jakarta Provincial Government to Announce Companies Illegally Dumping Waste

    access_time07-08-2026 remove_red_eye396 personDessy Suciati
  5. Thousand Islands Conducts Vehicle Emission Tests on Three Islands

    access_time07-08-2026 remove_red_eye386 personAnita Karyati