Pemasangan SGB di Depo LRT Kelapa Gading Dimulai

Segmental Girder Box Installation at Kelapa Gading LRT Begins

The first installation of the segmental girder box (SGB) at Light Rail Transit (LRT), Jalan Boulevard Utara, Kelapa Gading Timur, North Jakarta begins.

Launching gantry system is not using a crane car

PT Jakarta Propertindo (Jakpro) President Director, Satya Heragandhi said, until the end of this year, 1,300 SGBs are targeted to be installed at LRT lane as long as six kilometers, starting from Kelapa Gading Depot until Velodrome Rawamangan Station.

As the initial stage, he stated, 4 SGBs will be installed using launching gantry system.

LRT Construction Phase 1 Reaches 12.75 Percent

"Launching gantry system is not using a crane car. Once pulled up, it is directly assembled by the launcher," he expressed, Monday (5/29).

To speed up its installation, his side intends to prepare four units of launching gantry. Thus the project can be completed this year, and then continued with railway construction and train procurement in 2018.

"The pile is big enough and can withstand earthquakes with a magnitude of 5.2 on the Richter scale. Thus far the project has touched 21 percent," he closed.

Linked News
Popular News indeks
  1. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye516 personDessy Suciati
  2. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye502 personNurito
  3. Commission D Calls for Integrated Air Quality Monitoring System

    access_time06-11-2026 remove_red_eye486 personFakhrizal Fakhri
  4. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye463 personAldi Geri Lumban Tobing
  5. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye451 personDessy Suciati