 Pembangunan Breakwater Pulau Untung Jawa Mulai Dikerjakan

230 Meters Breakwater Has Been Installed in Untung Jawa Island

Seribu Islands Water Resources Sub-dept. said breakwater installment in north side of Untung Jawa Island that has been done from May, now reaches around 230 meters long.

From 600 meters, it has been done to 230 meters. Maybe after Eid, it can be finished

"From 600 meters, it has been done to 230 meters. Maybe after Eid, it can be finished," said Mustajab, Head Dept. of Seribu Islands Water Resources, Tuesday (6/13).

According to him, breakwater in the north side of the land will protect mangrove forest. It also can hold sand from coming back to the sea. Because waves in the island are greater than other island.

Breakwater on Lancang Island Finally Repaired

He continued, 11,000 tetrapods sea defenses have been installed to build 600 meters breakwater.

"Every 100 meters of breakwater installed, we open the path around 10 meters thus wave still can bring sand into the coast." he closed.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye618 personDessy Suciati
  2. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye567 personAldi Geri Lumban Tobing
  3. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye545 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye526 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye514 personNurito