MRT Railway Line Installation Has Touched 80 Percent
access_time May 09 2018 11:50 AM remove_red_eye 1133
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
Reported by Wuri Setyaningsih | Translated by Nugroho Adibrata
PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.
In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent
"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).
Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power.
MRT Project Has Touched 93.45 Percent"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.