Pemasangan Track Kereta MRT Jakarta Capai Lebih Dari 80 Persen

MRT Railway Line Installation Has Touched 80 Percent

PT Mass Rapid Transit (MRT) Jakarta President Director, William Sabandar disclosed, MRT railway line installation progress until April 30 has reached 80 percent of the total track length of 37,128 meters.

In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent

"In details, the railway at Depot Area has total length about 6,139 meters and has been installed up to 5,400 meters or 88 percent. While for the elevated road has been installed up to 15,192 out of the total length about 18,714 or 81 percent," he expressed, Tuesday (5/8).

Then for the underground line has been installed about 7,168 out of a total of 12,275 or 58 percent. Jakarta MRT will operate using electric power. 

MRT Project Has Touched 93.45 Percent

"70 MW is needed to operate it. That's why we continue to coordinate with PLN," he said.

Linked News
Popular News indeks
  1. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1022 personNurito
  2. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye942 personFolmer
  3. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye899 personDessy Suciati
  4. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye704 personAldi Geri Lumban Tobing
  5. Addressing Collapsed Road in Pulo Gadung is a Priority, Pramono Says

    access_time08-07-2026 remove_red_eye679 personDessy Suciati