 Pengerjaan Kolam Labuh di Pulau Lancang Pemasangan Tiang Pancang
.
photo Rudi Hermawan - Beritajakarta.id

20 Piles Have Been Installed on Lancang Island

20 points of piles are seen installed in order to smoothen an anchoring pool and improve the pier on Lancang Island. The total installation that reaches 66 points will be complete in the next three weeks.

Of 60 points, 20 out of them have been installed. Thus far the work has touched 15 percent

"Of 60 points, 20 out of them have been installed. Thus far the work has touched 15 percent," expressed Suherman, Section Head of Facility and Infrastructure Section for Seribu Islands Transportation Sub-dept., Friday (10/5).

After pile installation, it would be continued with plate installation for floor molding and casting. The work itself until now is in accordance with planning.

Pier Construction on Sebira Island Enters Planning Phase

"We believe it will finish in mid-December," he said.

Linked News
Popular News indeks
  1. Jakarta and Lampung Collaborate to Launch Lampung-in App

    access_time15-06-2025 remove_red_eye454 personDessy Suciati
  2. City Ready to Support Railway Transportation System in Bali

    access_time13-06-2025 remove_red_eye420 personBudhi Firmansyah Surapati
  3. City Council Fractions Deliver General Views on 2024 APBD Accountability

    access_time16-06-2025 remove_red_eye359 personFakhrizal Fakhri
  4. Cloudy Morning, Rainy Afternoon this Tuesday, BMKG Says

    access_time17-06-2025 remove_red_eye297 personDessy Suciati
  5. Jakarta Fair Kemayoran Begins, Hailing City’s 498th Anniversary

    access_time20-06-2025 remove_red_eye237 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik