Progres MRT Akhir Tahun 2018 98,10 Persen
.
photo istimewa - Beritajakarta.id

MRT Construction has Touched 98.10 Percent

Until December 2018, the progress of MRT construction has reached 98.10 percent. Its construction consists of depot and elevated section by 97.80 percent and underground section by 98.41 percent.

In overall, we have touched 98.10 percent

"In overall, we have touched 98.10 percent," expressed William P Sabandar, President Director of PT MRT Jakarta, Friday (12/28).

MRT Information Center in Dukuh Atas Inaugurated

According to him, some construction has not yet been completed, namely entrance and interior at a number of MRT stations.

"Entrance will be finished totally in February or March. While for interior will finish in January or February," he told.

Currently 16 MRT trains already exist at Lebak Bulus Depot. Each of them has six cars which in total reached 96 cars.

"In March, MRT construction is finished," he stated.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye716 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye603 personFolmer
  3. 49,101 Local and Foreign Tourists Swarm Monas

    access_time02-04-2025 remove_red_eye289 personBudhi Firmansyah Surapati
  4. Transjakarta Ready to Support People's Mobility This Eid

    access_time30-03-2025 remove_red_eye253 personAldi Geri Lumban Tobing
  5. S. Jakarta Transportation Sub-agency Optimizes Services at Tourist Spots

    access_time03-04-2025 remove_red_eye250 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik