MRT Construction has Touched 98.10 Percent

Until December 2018, the progress of MRT construction has reached 98.10 percent. Its construction consists of depot and elevated section by 97.80 percent and underground section by 98.41 percent.

In overall, we have touched 98.10 percent

"In overall, we have touched 98.10 percent," expressed William P Sabandar, President Director of PT MRT Jakarta, Friday (12/28).

MRT Information Center in Dukuh Atas Inaugurated

According to him, some construction has not yet been completed, namely entrance and interior at a number of MRT stations.

"Entrance will be finished totally in February or March. While for interior will finish in January or February," he told.

Currently 16 MRT trains already exist at Lebak Bulus Depot. Each of them has six cars which in total reached 96 cars.

"In March, MRT construction is finished," he stated.

Linked News
Popular News indeks
  1. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye495 personAldi Geri Lumban Tobing
  2. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye450 personDessy Suciati
  3. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye426 personAldi Geri Lumban Tobing
  4. Buildings on the Sidewalk in Front of Plumpang Transjakarta Bus Stop Demolished

    access_time30-09-2026 remove_red_eye409 personAnita Karyati
  5. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye385 personFakhrizal Fakhri