Progres MRT Akhir Tahun 2018 98,10 Persen

MRT Construction has Touched 98.10 Percent

Until December 2018, the progress of MRT construction has reached 98.10 percent. Its construction consists of depot and elevated section by 97.80 percent and underground section by 98.41 percent.

In overall, we have touched 98.10 percent

"In overall, we have touched 98.10 percent," expressed William P Sabandar, President Director of PT MRT Jakarta, Friday (12/28).

MRT Information Center in Dukuh Atas Inaugurated

According to him, some construction has not yet been completed, namely entrance and interior at a number of MRT stations.

"Entrance will be finished totally in February or March. While for interior will finish in January or February," he told.

Currently 16 MRT trains already exist at Lebak Bulus Depot. Each of them has six cars which in total reached 96 cars.

"In March, MRT construction is finished," he stated.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye759 personBudhi Firmansyah Surapati
  2. BPBD Prepares 403 Evacuation Sites to Mitigate Floods in Jakarta

    access_time08-11-2026 remove_red_eye528 personBudhi Firmansyah Surapati
  3. BI and Jakarta Government Deepen Investment, Creative Economy Collaboration

    access_time09-11-2026 remove_red_eye515 personAldi Geri Lumban Tobing
  4. Pramono Launches JEKATE Running 2026, Promotes Healthy Living

    access_time08-11-2026 remove_red_eye507 personDessy Suciati
  5. Tourism and Creative Economy Boost Jakarta's Economic Growth

    access_time08-11-2026 remove_red_eye468 personDessy Suciati