SDN 01 and 10 Duri Kepa Construction Continued

The construction of State Elementary Building (SDN) 01 and 10, Duri Kepa Urban Village, Kebon Jeruk Sub-District, West Jakarta, which has stopped after fire in 2012, is continued by West Jakarta Elementary Sub-Department. The building’s total renovation with budget Rp 4 billion is predicted to be completed late next year.

The target is at least the building’s foundations would already be built this year. As for its physical work, it starts next year

Syahroni (62), project executor of SDN 01 and 10 Duri Kepa building construction, explained that the demolition process of the school building that burned two years ago has been done since September. The new school building is planned to be built four-story high on a 364-square meter land.

“From the design we received, the school building will be four-story from previously only two-story,” he said, Tuesday (10/7).

Classrooms Burned, SDN 11 Tebet Timur Students Relocated

According to Syahroni, until this end of year his party will only clean up the remnants of burned building materials using a drilling machine and two heavy equipments. It is conducted because the project contractor will begin working on physical construction early next year.

“The target is at least the building’s foundations would already be built this year. As for its physical work, it starts next year,” he stated.

Meanwhile, Head of West Jakarta Elementary Sub-Department, Delly Indirayati, informed that post fire in 2012, the teaching and learning process in SDN 01 and 10 had to be moved to SDN 011 and 012 Duri Kepa next to it.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1150 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye847 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye828 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye780 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye757 personAldi Geri Lumban Tobing