Pengerukan Kali Apuran Cengkareng Barat Sudah 50 Persen

Apuran River Dredging is Targeted to Finish in Mid of July

West Jakarta Government continues to optimize flood prevention program, including to dredge Apuran River that located in Cengkareng Urban Village, Cengkareng. The dredging process has reached 50 percent and is targeted to finish in mid of July 2020.

Now, we have dredged 300 meters or 50 percent of the target

West Jakarta Water Resources (SDA) Sub-agency's Maintenance of Flood Control System for Raw Clean Water and Wastewater Section Head, Wawan stated, his side started dredging Apuran River since June 17. In order to increase capacity and flow of the river, his side planned to dredge it as long as 600 meters.

"Now, we have dredged 300 meters or 50 percent of the target," he informed, Tuesday (6/30).

East Jakarta Optimizes Flood Prevention Programs

His side deployed 14 personnel, 2 heavy equipments such as standard backhoe and amphibious excavator units, as well as 10 dump trucks with capacity 8 square meters and 3 tronton trucks with capacity 13 square meters.

"Until now, we have transported 403 cubic meters of mud. We plan to dredge around 70-100 centimeters," he closed.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye791 personFakhrizal Fakhri
  2. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye637 personAldi Geri Lumban Tobing
  3. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye629 personTiyo Surya Sakti
  4. Jakarta Newcomers Mostly in Productive Age

    access_time22-04-2026 remove_red_eye386 personAldi Geri Lumban Tobing
  5. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye371 personBudhi Firmansyah Surapati