South Jakarta SDA Accelerates Water Channel Construction on Jalan H. Saikin
access_time September 29 2020 09:49 PM remove_red_eye 1022
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
South Jakarta Water Resources (SDA) Sub-agency accelerated water channels construction work on Jalan H. Saikin, RW 08, Pondok Pinang Urban Village, Kebayoran Lama.
We build the channels as requested by local residents through Musrenbang
South Jakarta SDA Sub-agency Head, Mustajab stated, this channel construction has been started since August 13 on both sides of the road with length of 300 meters, width and depth of 1 meter each.
"Total length of both channels reaches 600 meters. We build the channels as requested by local residents through Musrenbang," he conveyed, Tuesday (9/29).
Pisang River Water Channel in Kebon Jeruk DredgedAccording to him, the channel construction is still being carried out by 12 personnel from Kebayoran Lama SDA Unit. They use excavator to dig the ground and install U-ditch concrete for the channels.
"We will accelerate our work. Our target is to complete it in three months," he closed.