Pengerukan Kali CIliwung Capai 80 Persen

Dredging Work in Ciliwung River Has Reached 80 Percent

To do it, we have sent two heavy equipments to the location

The dredging process for the Ciliwung River, Jatinegara, which is being carried out by the East Jakarta Water Resources Sub-agency, currently has reached 80 percent.

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto disclosed the river itself had 2,200 meters length with 20 meters width and 3 meters width.

LH Agency Collects 511 Cubic Meters Garbage from Ciliwung River

This dredging work started from under the bridge of Jalan KH Abdullah Syafi'i Kampung Melayu until Tong Tek Kebon Pala Bridge.

"To do it, we have sent two heavy equipments to the location," he explained, Wednesday (10/21).

It had been carried out since July 9 and was targeted to be complete by the end of this year.

Linked News
Popular News indeks
  1. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye660 personFakhrizal Fakhri
  2. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye653 personDessy Suciati
  3. Pramono: Jakarta Ready to Pay Out Holiday Bonus to ASN

    access_time04-03-2026 remove_red_eye559 personDessy Suciati
  4. Grab Your Umbrellas: Heavy Rain Expected to Soak Jakarta Today

    access_time06-03-2026 remove_red_eye556 personDessy Suciati
  5. Transjakarta`s Blok M–Soetta Airport Route Served by Metrotrans Low Entry Buses

    access_time05-03-2026 remove_red_eye513 personAldi Geri Lumban Tobing