Pengerukan Kali CIliwung Capai 80 Persen
.
photo Nurito - Beritajakarta.id

Dredging Work in Ciliwung River Has Reached 80 Percent

To do it, we have sent two heavy equipments to the location

The dredging process for the Ciliwung River, Jatinegara, which is being carried out by the East Jakarta Water Resources Sub-agency, currently has reached 80 percent.

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head Puryanto disclosed the river itself had 2,200 meters length with 20 meters width and 3 meters width.

LH Agency Collects 511 Cubic Meters Garbage from Ciliwung River

This dredging work started from under the bridge of Jalan KH Abdullah Syafi'i Kampung Melayu until Tong Tek Kebon Pala Bridge.

"To do it, we have sent two heavy equipments to the location," he explained, Wednesday (10/21).

It had been carried out since July 9 and was targeted to be complete by the end of this year.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye553 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye445 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye309 personBudhi Firmansyah Surapati
  4. Jakartans Invited to Participate in HPSN 2025 Event

    access_time21-02-2025 remove_red_eye301 personAldi Geri Lumban Tobing
  5. 41 Wild Cats in Cikoko Sterilized

    access_time21-02-2025 remove_red_eye295 personTiyo Surya Sakti