Channels Normalization on Jalan Patra and Mangga I Reaches 55 Percent

Until now it has reached 55 percent ongoing and is targeted to be complete on October 15

The water channels normalization work on Jalan Patra and Jalan Mangga I, Duri Kepa, Kebon Jeruk, West Jakarta has reached 55 percent.

West Jakarta Water Resources (SDA) Sub-agency's Development and Drainage Improvement Division Head Imam Prasetyo said it had been ongoing since October 22.

Rawa Lindung Reservoir Dredged from Waste

He explained, the channel normalization on Jalan Patra was up to 325 meters length with 150 centimeters depth and width. Then on Jalan Mangga I, it was done up to 145 meters with 80 centimeters width and depth.

"Until now it has reached 55 percent ongoing and is targeted to be complete on October 15," he said, Wednesday (11/11).

It was done to maximize water holding capacity and to smoothen water flow into retention pond or locally known as olakan towards Sekretaris River when rain poured.

"By so we can avoid puddles on Jalan Patra, Jalan Asem, Jalan Mangga and its surroudings," he closed.

Linked News
Popular News indeks
  1. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye795 personBudhi Firmansyah Surapati
  2. W. Jakarta SDA Constructs Channel on Jalan Nurul Muslimin I Kembangan

    access_time04-11-2024 remove_red_eye780 personTP Moan Simanjuntak
  3. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye479 personFolmer
  4. Tanah Tinggi Residents Participate in Computer Operator Training

    access_time02-11-2024 remove_red_eye377 personBudhi Firmansyah Surapati
  5. 104 Wild Cats in Kebayoran Lama Sterilized

    access_time07-11-2024 remove_red_eye346 personTiyo Surya Sakti