Bojong Reservoir Dredging Targeted to Finish By the End of This Month

West Jakarta Water Resources (SDA) Sub-agency accelerates mud dredging work in Bojong Reservoir on Jalana Telaga Bojong, Rawa Buaya, Cengkareng, West Jakarta.

We carry out the work from November 17 and target it to finish by the end of December

"We carry out the work from November 17 and target it to finish by the end of December," conveyed Wawan Kurniawan,  SDA Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, on Tuesday (12/1).

His side deployed 2 heavy equipment with amphibious and long excavator type and 8 dump trucks to dredge mud from reservoir with depth of 3 meters and 1.6 hectares wide.

Mampang River Along Jl. Pondok Karya Dredged

"We dredge the mud thus reservoir can drain water optimally to anticipate inundation in the surrounding area," he mentioned.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye865 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye421 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye369 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye354 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye343 personAldi Geri Lumban Tobing
close