Proyek JIS, Rampungkan Lapangan Latih
.
photo Wuri Setyaningsih - Beritajakarta.id

Jakarta International Stadium Construction Accelerated

The process of Jakarta International Stadium (JIS) construction project has touched 38.69 percent.

We are currently completing the pierhead in the main column

Corporate Communication & Commercial for JIS Project, Arnold Kindangen mentioned, entering the 66th week, its process has touched 38.69 percent. It has entered the finishing stage of east ramp and roof structure assembling.

"We are currently completing the pierhead in the main column. The construction uses slipform concept," he conveyed, Wednesday (12/9).

Entering 64th Week, JIS Construction Touches 36.7 Percent

For construction on the training field, he continued, is still in the finishing stage for stands and lamppost installation.

"JIS area in total reaches 23 hectares with land under RAP of 1.2 hectares," he stated.

According to him, JIS area is expected to reach 235,127 square meters with audience capacity of 82,000 people.

Linked News
Popular News indeks
  1. Environment Agency Supports Efforts to Comply with Vehicle Emissions Test Regulations

    access_time12-03-2025 remove_red_eye585 personAldi Geri Lumban Tobing
  2. Transjakarta Presents Jakarta Symphony Every Saturday Afternoon

    access_time10-03-2025 remove_red_eye470 personAldi Geri Lumban Tobing
  3. Rano Supports Schools to Organize Study Tours to Museums

    access_time08-03-2025 remove_red_eye376 personBudhi Firmansyah Surapati
  4. TMII Launches Jelajah Cerita Ramadan Program with Umroh Grand Prize

    access_time08-03-2025 remove_red_eye374 personNurito
  5. Council Urges Health Agency to Collaborate Across Regions to Prevent TB Spread

    access_time10-03-2025 remove_red_eye371 personFolmer

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik