Progres Pembangunan JIS Sudah 36,7 Persen

Entering 64th Week, JIS Construction Touches 36.7 Percent

Construction project of Jakarta International Stadium (JIS) in Papanggo Village, Tanjung Priok, North Jakarta still continued even in the midst of COVID-19 pandemic situation. Entering the 64th week, its progress had touched more than 30 percent.

Deviation is getting smaller, it means Jakpro and KSO still committed to continue and accelerate the construction

Corporate Communication & Commercial for JIS Project, Arnold Kindangen mentioned, until end of November or 64th week, the process of JIS construction had reached 36.7272 percent.

"Deviation is getting smaller, it means Jakpro and KSO still committed to continue and accelerate the construction," he conveyed, Monday (11/30).

Jakpro Disbursed Fifth Phase of Resettlement Action Plan Compensation

According to him, deviation occurred due to weather factors and the impact of COVID-19 pandemic which resulted in delays in imported materials supply.

"But now the condition is back to normal, all materials have been shipped and used for JIS construction. Contribution of the roof is quite large to reduce deviation," he said.

For information, JIS used lifting method for the construction.

"For the lifting process, JIS uses 8 main columns with pearhead. Those 8 columns are used to divide the roof load about 4,000 tons," he mentioned.

The process had entered fire fighting, plumbing, and ducting stages. Its focus was on completing the training field stands in December 2020.

"JIS project is oriented to empower domestic entrepreneurs by using many domestic vendors and materials to support economic recovery during the pandemic," he stated.

Until the 64th week, JIS project had absorbed more than 2,000 workers or added 100 workers every week.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye1268 personFakhrizal Fakhri
  2. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye620 personDessy Suciati
  3. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye600 personAnita Karyati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye589 personFolmer
  5. Welcoming BTS's Concert in December 2026, Jakarta is Dressed in Purple

    access_time16-11-2026 remove_red_eye568 personFakhrizal Fakhri