Jakarta International Stadium Construction Accelerated

The process of Jakarta International Stadium (JIS) construction project has touched 38.69 percent.

We are currently completing the pierhead in the main column

Corporate Communication & Commercial for JIS Project, Arnold Kindangen mentioned, entering the 66th week, its process has touched 38.69 percent. It has entered the finishing stage of east ramp and roof structure assembling.

"We are currently completing the pierhead in the main column. The construction uses slipform concept," he conveyed, Wednesday (12/9).

Entering 64th Week, JIS Construction Touches 36.7 Percent

For construction on the training field, he continued, is still in the finishing stage for stands and lamppost installation.

"JIS area in total reaches 23 hectares with land under RAP of 1.2 hectares," he stated.

According to him, JIS area is expected to reach 235,127 square meters with audience capacity of 82,000 people.

Linked News
Popular News indeks
  1. JRF, Ye Concert Inject Rp 625 Billion into Jakarta's Economy

    access_time26-10-2026 remove_red_eye544 personDessy Suciati
  2. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye522 personAldi Geri Lumban Tobing
  3. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye507 personFolmer
  4. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye506 personAldi Geri Lumban Tobing
  5. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye502 personNurito