Jakarta International Stadium Construction Accelerated

The process of Jakarta International Stadium (JIS) construction project has touched 38.69 percent.

We are currently completing the pierhead in the main column

Corporate Communication & Commercial for JIS Project, Arnold Kindangen mentioned, entering the 66th week, its process has touched 38.69 percent. It has entered the finishing stage of east ramp and roof structure assembling.

"We are currently completing the pierhead in the main column. The construction uses slipform concept," he conveyed, Wednesday (12/9).

Entering 64th Week, JIS Construction Touches 36.7 Percent

For construction on the training field, he continued, is still in the finishing stage for stands and lamppost installation.

"JIS area in total reaches 23 hectares with land under RAP of 1.2 hectares," he stated.

According to him, JIS area is expected to reach 235,127 square meters with audience capacity of 82,000 people.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1452 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1176 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye982 personFolmer
  4. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye885 personAldi Geri Lumban Tobing
  5. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye864 personAldi Geri Lumban Tobing